Septic Rings and Forms

Things are changing quickly! We had the septic seep pit liners delivered. We have to have our primary AND secondary septic pits fully lined. Each pit is about thirty feet deep so we have a lot of these things! Also the grade beam and stem wall forms are nearing completion and on Thursday we will begin pouring these. I’ll try do an update on Thursday as we leave for Vietnam on Friday for the John Vo KG wedding extravaganza!

Our foreman

Stem wall formsCloser view of formsSeptic LinerSeptic Liner with DogsView up lot with forms

Grade Beams

Not sure if this counts as being out of the ground, but we are getting close. Last week the guys came up and tied all the grade beams. They need to finish the forms, get the moment frame installed and then next week we should be ready to pour the concrete. Once we have that done on to stem walls and then…framing. You should see some big changes over the next four weeks or so. Here are some pictures, and the cool thing is that you can start to see the outline of the house. 

IMG_0203.JPG

 

IMG_0193.JPG

 

IMG_0182.JPG

 

IMG_0186.JPG

 

IMG_0198.JPG

 

IMG_0195.JPG

 

IMG_0183.JPG

 

IMG_0181.JPG

 

IMG_0179.JPG

How to you build and keep your neighbors happy?

Building a house is noisy, dusty, and starts early in the morning. So how then do you keep your neighbors from wanting to kill you by the end? This is something that I have been trying to figure out. I figured we should probably do a few things in the name of neighborly relations such as we don’t drill and do other really noisy things on weekends or before 8am. However, everything we do is noisy in some way and we don’t have that much day light to work with during the winter. The rules for construction are from 7am to 9pm Monday through Friday and from 8am to 6pm on Saturday. We cannot work on Sundays. So far I have kept people from working on Saturdays because I know how bad it sucks to deal with the noise, but once we are done with the heavy drilling I am tempted to go back to building per the rules. If I don’t work until 8am and don’t work on Saturday I am essentially loosing two days a week of time. Multiplied out over the course of the year that it is going to take that is a about 100 days of work! If we take an hour out of each day that comes to about a day a week. Right now my neighbor would like it if I don’t start until 8am but that would add 1/8 to the cost of the project.

Basically, we need to get this thing build as soon as possible for as little as possible. However, I don’t want to have people sending me death threats you know? Oh and I want to move into a trailer on the property, we’ll see what Jenn thinks of that ";-)"

Last of the Caissons

Yesterday we put in the last of the caissons! Once again the cement truck showed up about an hour and a half late, but we where able to get everything done anyway. I am going to try something new and use lightbox for the images. Just click one of the thumbnails to see the slideshow and captions.

IMGP1896.JPG IMGP1897.JPG IMGP1898.JPG
IMGP1903.JPG IMGP1907.JPG IMGP1908.JPG
IMGP1909.JPG IMGP1911.JPG IMGP1913.JPG
IMGP1914.JPG IMGP1915.JPG IMGP1917.JPG
IMGP1918.JPG

Shadow line detail and lighting

Our friend Dudley drew up a shadow line detail for us to try save some money by not using the Fry Reglet reveal. 

shadow_detail.jpg  

 

Basically you put a 2×4 down while you hang the dry wall then pull it out paint the framing black and put in a standard L-corner bead. Also, Steve pointed out this really cool company which makes cans for CCFC and LED lights. Something we really should look into. The company is called Axiom and their products look pretty cool.