Grade Beams

Not sure if this counts as being out of the ground, but we are getting close. Last week the guys came up and tied all the grade beams. They need to finish the forms, get the moment frame installed and then next week we should be ready to pour the concrete. Once we have that done on to stem walls and then…framing. You should see some big changes over the next four weeks or so. Here are some pictures, and the cool thing is that you can start to see the outline of the house. 

IMG_0203.JPG

 

IMG_0193.JPG

 

IMG_0182.JPG

 

IMG_0186.JPG

 

IMG_0198.JPG

 

IMG_0195.JPG

 

IMG_0183.JPG

 

IMG_0181.JPG

 

IMG_0179.JPG

How to you build and keep your neighbors happy?

Building a house is noisy, dusty, and starts early in the morning. So how then do you keep your neighbors from wanting to kill you by the end? This is something that I have been trying to figure out. I figured we should probably do a few things in the name of neighborly relations such as we don’t drill and do other really noisy things on weekends or before 8am. However, everything we do is noisy in some way and we don’t have that much day light to work with during the winter. The rules for construction are from 7am to 9pm Monday through Friday and from 8am to 6pm on Saturday. We cannot work on Sundays. So far I have kept people from working on Saturdays because I know how bad it sucks to deal with the noise, but once we are done with the heavy drilling I am tempted to go back to building per the rules. If I don’t work until 8am and don’t work on Saturday I am essentially loosing two days a week of time. Multiplied out over the course of the year that it is going to take that is a about 100 days of work! If we take an hour out of each day that comes to about a day a week. Right now my neighbor would like it if I don’t start until 8am but that would add 1/8 to the cost of the project.

Basically, we need to get this thing build as soon as possible for as little as possible. However, I don’t want to have people sending me death threats you know? Oh and I want to move into a trailer on the property, we’ll see what Jenn thinks of that ";-)"

Last of the Caissons

Yesterday we put in the last of the caissons! Once again the cement truck showed up about an hour and a half late, but we where able to get everything done anyway. I am going to try something new and use lightbox for the images. Just click one of the thumbnails to see the slideshow and captions.

IMGP1896.JPG IMGP1897.JPG IMGP1898.JPG
IMGP1903.JPG IMGP1907.JPG IMGP1908.JPG
IMGP1909.JPG IMGP1911.JPG IMGP1913.JPG
IMGP1914.JPG IMGP1915.JPG IMGP1917.JPG
IMGP1918.JPG

Shadow line detail and lighting

Our friend Dudley drew up a shadow line detail for us to try save some money by not using the Fry Reglet reveal. 

shadow_detail.jpg  

 

Basically you put a 2×4 down while you hang the dry wall then pull it out paint the framing black and put in a standard L-corner bead. Also, Steve pointed out this really cool company which makes cans for CCFC and LED lights. Something we really should look into. The company is called Axiom and their products look pretty cool.

  

Happy New Year

Well it is officially 2008 and has been for about 48 hours now. To start off the year we got some good news. First, we received a new bid for our fancy septic system that was $12k less than our original bid. That is pretty nice! Like all things that LA County is making us do, this septic system is totally over the top. It is created by a company called MicroSepTec.

 

microseptic.jpg

 

The MicroSepTec EnviroServer ES (yep that is right EnviroServer!)

 

It is a five chamber system that basically puts out extremely clean water with no particulates greater than 1/16″ in size, and the thing can be remotely monitored! The second piece of news is that we might have found a way to build a detail that we really wanted. The architects had spec’d a shadow line reveal using a product from Fry Reglet called a Z-reveal. Sean said we could save about $6k from removing this detail so we pulled it. However, talking to our friend Dudley, he mentioned another option that wouldn’t require anything other than a standard L-bracket corner molding and some black paint. I have the drawing at home and will post ASAP. I hope this will work or that some similar option will because I think it is a really cool detail. Based Dudley’s drawings and google it seems there should be plenty of options to do shadow reveals.

 

As for the progress on the house, well, it has been slow. We had a number of days we had to wait due to rain and then the holidays came. Now that they are over we have a nice storm coming our way!

 

rain_coming.jpg

 

The storm is supposed to hit Thursday night, we are hoping to be able to start pouring concrete on Tuesday. Right now our drillers are back on site and clearing out the remaining three caisson holes. They are going to drill a few feet extra in case we get mud forming at the bottom of the holes. The biggest change from my last posting is that we have re-graded the hill to a more natural state. Other than that we have few changes.

 

IMGP1891.JPG

 

You can see the four top caissons and get a feel for the natural grade.

 

IMGP1890.JPG

 

That is the natural grade of the top, it is pretty steep! The flat pad is where the drill will be working today.

 

IMGP1894.JPG

 

Looking up at our site with a new grade.

 

IMGP1893.JPG

 

The drill rig is waiting for its driver.

 

IMGP1895.JPG

 

Another gorgeous day!

 

Concrete Pour

On Wednesday we poured all but three of the remaining caissons (we have ten total!). I missed the crane putting the steel into the ground but was able to get to the site before the concrete trucks. This wasn’t too hard as the trucks where over an hour and a half late. IMGP1846.JPG Here you can see the two cassions for the bottom corners fo the house. The second one is a bit hidden by the dirt. Once these are poured and we have fixed the grading there will be concrete and steel grade beams which connect these. All the caissons will be connected via grade beams. Then stem walls will be built on top of which we will do framing. Here is an example of grade beams connecting to a caissons. The stem wall is then built up over the grade beam. gradebeams.jpg IMGP1848.JPG Since we where waiting for the truck Sean had the guys build some steps after he took a nasty fall. All that loose dirt is slippery! IMGP1857.JPG We had to close off Las Flores Canyon in one direction for the trucks. By the time the concrete arrived the radios the guys where using had run out of batteries! IMGP1860.JPG This is what concrete guys do when trucks are late! IMGP1859.JPG This is what the steel guys do, they call and ask where the F*** is the mud! IMGP1861.JPGIMGP1862.JPG Finally! The truck arrives, we had a truck schedule to come every 1/2 hour and had seven trucks total schedule to come on Wednesday. IMGP1865.JPG Before anyone can start the inspector has to take samples, however, the samples are tested off site. Which begs the question, what does one do if the samples fail the compression tests? IMGP1868.JPG The concrete is poured into the pump and carried via hoses down to the caisson holes. IMGP1867.JPG IMGP1869.JPG The guys are pouring the concrete in to the holes and holding the caisson cage upright as the concrete goes in. IMGP1870.JPG IMGP1871.JPG It takes two trucks of concrete before you can even see the stuff coming towards the top of the hole. IMGP1875.JPG Here it is at the end of the day. There where 5 total done on wednesday. IMGP1882.JPG Wednesday evening was beautiful! You could see Catalina and Palos Verdes from our lot. Once this house is done it is going to be beautiful to live up here. IMGP1889.JPG Looking back up the lot, some day we will be out of the ground and have a structure! 

Caissons

I’m working on the latest update which should go out later today. In the meantime I thought I’d upload some pictures of the steel which will hold our house up. The guys did some impressive work, this is some serious hardware! 

IMGP1810.JPG IMGP1808.JPG

 IMGP1812.JPG IMGP1813.JPG 

Water Meter Is Installed

Our water meter was installed over the last week. Here is what $14k buys you!

 

 Pretty impressive? Well not all that exciting to look at, but I am sure it will be nice to have some water up there to keep dust down, etc. Unfortunately, it feels like we are making much slower progress on the drilling front. It turns out that not only can we not drill from the road but that we cannot drill all the top holes at the same time! Additionally, in order to drill the top holes we had to cover over the middle four. In addition, we will have to re-drill all holes before putting the steel and concrete in to make sure that we have a solid footing. This is all sounding very expensive. Hopefully, I can cajole my friends to help with painting and convince Chris (Mom’s boyfriend/finance/partner/etc) to come up and help with some of the interior finish work. Chris, we can do it when the surf is good! I finally got in touch with Verizon, however, Charter who said they were going to move things still is a no-show. I’ll be meeitng with the Verizon engineer today. As you can see the lines are super low. 

 

 As you can see I can easily grab the wires. I was SOOO tempted to yank, but then I think my neighbors might get a bit mad since they would loose their service. 

 

No more holes.

 I’ll be up there again today, and will report back. Hopefully the structural engineer made it up to inspect the steel so we can push forward. Progress uber alles.  

Steel is all tied up

The guys finished tying up the steel caissons and we should finish drilling this week. In other news, Verizon is a pain in the ass! If you look over some of the photos you can see cables.

 

It is hard to see but there are two cables coming off that pole.

 

 

The cable is REALLY LOW!

 Anyway, I am trying to get them to move the cables. You would think that would be difficult but not impossible. To date I have been on hold for several hours and finally got a real person’s name and number. If only I could get in touch with Tommy Hinson, perhaps my problems will be solved? I’ve talked to people in repair, safety and other customer support areas to no avail. The worst was repair, the manager Maria informed me that my neighbors would have to file an order to move Verizon’s line off my property! It took almost an hour to get through to someone that this wasn’t my neighbor’s issue but was theirs. We shall see, next up calling Charter Communications. 

Here are some pictures of the new steel.

 

 

As you can see there are different sizes since each hole is a slightly different width. The front ones being much larger than the back ones.

 

 

 

The site has changed a lot since we first started!

 

 

This is where the steel will go! That hole is deep.

   

Steel is Delivered

The steel came in yesterday! Also, we got through four more caissons so we are getting much closer to completing that aspect. However, we might be running into problems with the top four. We originally planned on hitting those from the top, however, due to the placement the drill rig would have to close off both lanes of Las Flores. So, we are going to have to approach those from the bottom. Also, the bottom two holes might incur additional “coring” fees. Boo! I guess there will always be some sort of cost overrun, but I sure do want to keep these down! As always, here are some pictures.

 

Working on the sixth caisson

 

 

This steel will be going down into the holes once it is tied up. Thanks to our neighbor for lending their front loader to get these suckers up onto the property!

 

 

Those bundles are what will be used to tie the long steel beams together.

 

 

This is the most people we have had on the site to date. The guys are placing the steel beams up to tie together.